SV-CL-01 „The upgrading of the water management systems, water storage reservoirs and water pumping stations in the localities of Suceava and Fălticeni”
LOT 1 - „Suceava water distribution system”
Contractor: S.C. OCSA CONSTRUCȚII ȘI INFRASTRUCTURĂ S.R.L.
Contract price: Lei 7,190,475.69 (VAT excluded)
Contract signing date: October 26th 2023
Duration of the contract: 31 months starting from the work commencement date, comprising a 6-month work design phase and a 25-month construction phase, to be followed by a 60-month defect notification period.
Commencement date for designing activities: November 9th 2023
The scope of the contract SV-CL-01, LOT 1 is the rehabilitation of the Suceava water supply system, specifically: the Mihoveni SP1 raw water pumping stations, the Mihoveni raw water transmission main, the water storage reservoir (with a 500 m3 capacity) located at the Mihoveni raw water treatment station, and the water pumping stations in the city of Suceava (Zamca II, Sfântu Ilie)
Contract implementation status: contract is underway