SV-CL-08 “The upgrading of water sources, water management facilities and water storage capacities in the localities of Câmpulung Moldovenesc and Vatra Dornei”

LOT 1 – “Câmpulung Moldovenesc water distribution system”

Contractor: The Joint Venture MAGHEBO S.R.L. (Leader) – GROUP CONSTRUCT BUCOVINA
S.R.L. – TOPGEOSYS S.R.L.
Contract price: Lei 21,750,240.34, VAT excluded
Contract signing date: January 30th, 2026
Duration of the contract: 31 months starting from the work commencement date, comprising a 6-month work design phase and a 25-month construction phase, to be followed by a 60-month defect notification period.
Commencement date of the design activities: February 16th, 2026
The scope of contract SV-CL-08, LOT 1 includes rehabilitation works for the following objectives that are part of the Câmpulung Moldovenesc drinking water supply system:
– the Sadova water intake facility (located on the right bank of the Moldova River, near the commune of Sadova)
and the Aeroport water intake facility (located on the right bank of the Moldova River, on the western side
of the locality of Câmpulung Moldovenesc);
– the transmission main that conveys drinking water from the Sadova water intake facility to the
Runc reservoirs, as well as the transmission main that conveys drinking water from the
Aeroport water intake facility to the Măgura reservoirs;
– the Măgura drinking water reservoirs (with a storage capacity of 2 x 1,000 m3) and the Runc drinking water reservoirs (with a storage capacity of 2 x 500 m3).

Contract implementation status: contract under execution