SV-CL-10 The rehabilitation of the Waste Water Treatment Plant in the locality of Câmpulung Moldovenesc”

Contractor: Joint Venture S.C. TERRA DINAMIC S.R.L. (Leader) - S.C. TERRA DINAMIC AG S.R.L. - S.C. DAVOGDARIS S.R.L.


Contract value: Lei 20,095,128 (VAT excluded)


Contract signing date: October 29th 2025


Duration of the contract: 35 months starting from the work commencement date, comprising a 6-month design phase and a 29-month construction phase, to be followed by a 60-month defect notification period


Commencement date of the design work: November 17th 2025


The overall objective of the contract SV-CL-10 is the rehabilitation, the tehnological upgrading and the extention of the current facilities existing at the wastewater treatment plant located in the locality of Câmpulung Moldovenesc in order to ensure the proper treatment of the collected sewage and the discharge of the treated wastewater under safe conditions for both the public health and the environment.


The WWTP is designed for a population equivalent of 20,323 PE and will be equipped with the following advanced wastewater treatment facilities: a mechanical stage, a biological stage and a sludge treatment stage. Also, the WWTP will be equipped with a SCADA monitoring system.

Contract implementation status: contract is underway