SV-CL-19 „The construction of the Waste Water Treatment Plant in the locality of Marginea”
Contractor: Joint Venture ARCIF AG S.R.L. – AEG TEHNOLOGY S.R.L. – AQUA TECHNOLOGY DESIGN S.R.L.
Contract price: Lei 19,193,591.35 (VAT excluded)
Contract signing date: October 31st 2022
Duration of the contract: 35 months starting from the work commencement date, comprising a 6-month design phase, a 24-month construction phase and a 5-month testing and commissioning phase, which will be followed by a 60-month defect notification period
Design work commencement date: November 28th 2022
The WWTP to be built under the contract SV-CL-19 is designed for a population equivalent of 8,876 P.E. and will be equipped with the following advanced wastewater treatment facilities: a mechanical stage, a biological stage and a sludge processing stage. Also, the new WWTP will be equipped with a SCADA monitoring system.
Contract implementation status: contract is underway