SV-CL-20 „The rehabilitation of the Waste Water Treatment Plant in the locality of Siret”
Contractor: S.C. OCSA CONSTRUCȚII ȘI INFRASTRUCTURĂ S.R.L.
Contract price: Lei 21,258,320.74 (VAT excluded)
Contract signing date: July 11th 2023
Duration of the contract: 35 months starting from the work commencement date, comprising a 6-month design phase and a 29-month construction phase, to be followed by a 60-month defect notification period
Design work commencement date: July 25th 2023
The WWTP to be built under the contract SV-CL-20 is designed for a population equivalent of 8,631 P.E. and will be equipped with the following advanced wastewater treatment facilities: a mechanical stage, a biological stage and a sludge processing stage. Also, the rehabilitated WWTP will be equipped with a SCADA monitoring system.
Contract implementation status: contract is underway